702.01
BUILDING AND SITES
Selection of an Architect/Engineer
Architects or engineers for major building and district master plan projects shall
be interviewed and reviewed by the Superintendent or superintendent's designee
or committee appointed to a specific building project. The recommendation shall be presented to the Board
for their consideration and official approval for the specific project under
consideration.
-
Legal Reference: Code of Iowa Chapter 544A
-
Cross Reference: Administrative Regulation
702.01A -
By action of the Board 12/13/76; Revised 6/13/83; Reviewed 8/9/93; Revised
6/12/00; Revised 04/27/09
-
Edited 04/09
702.02
BUILDING AND
SITES
Procedures with
Architects/Engineers During Construction
The following
guidelines shall be followed with relation to
procedures with architects/engineers during any
construction period:
1. Any
changes requested by the Board, architect, and/or
administration shall be submitted in writing to the
Superintendent, or superintendent designee, who
shall request the architect to obtain prices.
Recommendations shall be submitted to the Board for
action. When the construction project needs to
continue, the Change Order may be submitted after
the fact at the next Board meeting. If the Board
approves, three copies of the Change Order will be
prepared, and the Superintendent or superintendent’s
designee will sign for the Board, with copies
to go to the Board.
2. Estimated
costs less than $25,000 that must receive
immediate action in order to continue job progress
shall be referred to the Chief Financial Officer for
approval, with notice to the Board President. Major
Change Orders, $25,000 or more, will be given to the
Board on a monthly basis.
3. The
architect shall check payment request and submit
voucher to the Superintendent or
superintendent’s designee. The
administration, with Board approval, shall have the
authority to make payments that are under contract.
4.
The architect shall submit reports of work
progress to the Superintendent or superintendent’s
designee each month.
5. Regular
job conferences shall be scheduled for each project.
The Superintendent shall appoint an administrator to
represent the District.
6. The
architect shall keep the Superintendent or
superintendent’s designee apprised of the
contractors’ performance to include delays affecting
the completion date. Major delays will be reported
to the Board.
·
By action of the Board 12/13/76, 10/13/80;
Revised 6/13/83, 12/10/84; Reviewed 8/9/93; Revised
6/26/00; revised 04/27/09; Revised 9/14/09
·
Edited 04/09; 9/09
|